CAREC Transport Corridor 1 (Zhambyl Oblast Section) Investment Program - Tranche 4

CAREC Transport Corridor 1 (Zhambyl Oblast Section) Investment Program - Tranche 4

Locations

Type

Road

Status

Completed

Total Reported Cost

131.0 million USD

Initiatives

Start Date

2011

Start of Construction

Jan. 27 2012

Planned Completion Date

May 21 2014

Funders

Source(s) Amount
112,000,000 USD
19,000,000 USD

Description

Road reconstruction project at “Almaty-Kordai – Blagoveschenka – Merke – Tashkent – Termez” section in Kazakhstan, close the the border with the Republic of Kyrgyzstan.

Project is in large financed by the Asian Development Bank, with the agreement of the Government of Kazakhstan.