Integrated Road Investment Program-Tranche 3

Locations

Type

Road

Status

Under Construction

Total Reported Cost

233.9 million USD

Initiatives

Start Date

Nov. 23 2015

Start of Construction

Planned Completion Date

Sept. 30 2021

Contractors

Consultants

Funders

Source(s) Amount
25,000,000 USD
175,000,000 USD
23,000,000 USD

Description

Tranche 3 concerns the second slice of the rural development project in Sri Lanka, which includes improving existing rural roads in Gelle, Matara, and Hambanthota Districts. The total length of roads subject for rehabilitation is 586km. The goal of the project is to provide access to essential services, such as education and markets.