Tosontsengel - Uliastai Road (Construction) (PPP)

Locations

Type

Road

Status

Under Construction

Total Reported Cost

Initiatives

Start Date

2016

Start of Construction

July 31 2017

Planned Completion Date

2018

Implementers

Operators

Funders

Source(s) Amount
None USD

Description

The Government of Mongolia plans to complete the aimag centers with paved roads in 2016-2020 to complete the 114 km paved road in Tosontsengel-Uliastai. The road was officially opened by Minister of Road and Transportation D.Ganbat, Deputy Speaker of the State Great Hural Ya. Sanjmyatav and the local authorities and the local people on the 26th of this month. The road will be a 3-lane road with 7 meters wide and 5 cm thick asphalt pavement.